Prepare time scaled version network and histogram for EST and LST schedule.

Following table shows activities, their durations and labour requirement.

Activity Immediate Predecessor Duration (days) Labours
A - 4 9
B - 2 3
C - 2 6
D - 4 4
E B 3\ 8\
F C 2 7
G D, F 3 2
H E, G 4 1

Prepare time scaled version network and histogram for EST and LST schedule. Which schedule will you prefer? Why?


1 Answer
0
18views
Activity Immediate Predecessor Duration (days) EST EFT LST LFT Labours
A - 4 0 4 7 11 9
B - 2 0 2 2 4 3
C - 2 0 2 0 2 6
D - 4 0 4 0 4 4
E B 3 2 5 4 7 8 …