Draw network and determine project duration, critical path. Also calculate total float & free float for all the activities.

Mumbai University > Civil Engineering > SEM 8 > Construction Management

Marks: 12M

A Project consists of following activities. Their sequence and duration are also given in following table. Draw network and determine project duration, critical path. Also calculate total float & free float for all the activities.

A B C D E F G H I J
Activity 1-2 1-3 2-3 2-4 4-6 3-6 3-5 5-6 5-7 6-7
Duration 2 3 7 2 2 5 3 1 4 6
1 Answer
0
874views

EFT=EST+d, LST=LFT-d …………………….. (d=Duration)

Activity Duration EST EFT LST LFT T.F F.F
A(1-2) 2 0 2 0 2 0 0
B(1-3) 3 0 3 6 9 6 6
C(2-3) 7 2 9 2 9 0 0
D(2-4) 2 2 4 10 12 8 0
E(4-6) 2 4 6 12 14 …