2
2.5kviews
A small project consists of following activities. Draw network. Mark critical path. Determine project duration.

Mumbai University > Civil Engineering > SEM 8 > Construction Management

Marks: 12M

A small project consists of following activities. Draw network. Mark critical path. Determine project duration. Find out the values of all type of float:-

Activity Preceding,Activity Duration (days)
P - 3
Q - 5
R - 7
S P, Q 5
T S, R 3
U S, R 4
V S, R 6
W U, V 8
X U, V 6
Y T, W 4
1 Answer
1
25views
Activity Preceding,Activity Duration (days) EST EFT LST LFT TF FF Int F Ind F
P - 3 0 3 2 5 2 0 2 0
Q - 5 0 5 0 5 0 0 0 0
R - 7 0 7 3 10 3 3 0 3
S P, Q …

Create a free account to keep reading this post.

and 3 others joined a min ago.

Please log in to add an answer.