written 8.0 years ago by |
Information Tech Project Management - May 2015
Information Technology Engineering (Semester 6)
TOTAL MARKS: 100
TOTAL TIME: 3 HOURS
(1) Question 1 is compulsory.
(2) Attempt any four from the remaining questions.
(3) Assume data wherever required.
(4) Figures to the right indicate full marks.
Answer any one question from Q1 and Q2
1 (a) Explain Macgregor's theory of X and Y for motivation.(4 marks)
1 (b) Explain Maslow's need hierarchy theory of motivation.(6 marks)
10 (a) Write short note on:
i) Re-engineering
ii) Business process management
iii) Project management tools.(12 marks)
10 (b) What is Software Process Improvement?(6 marks)
2 (a) What is the difference between programmed and non programmed decision?(4 marks)
2 (b) What are various career fields possible for engineering graduates?(6 marks)
Answer any one question from Q3 and Q4
3 (a) Explain the process of requirement analysis and specification process with the help of diagram.(4 marks)
3 (b) Write short note on:
i) ISO 9000
ii) Six sigma(6 marks)
4 (a) State the difference between:
i) High level design and detailed design.
ii) Unit testing and integration testing.(6 marks)
Answer any one question from Q5 and Q6
5 (a) Explain four major sections of project management plan.(8 marks) 5 (b) Explain in short importance of cost management and time management in project execution.(8 marks) 6 (a) Explain configuration management process in detail.(8 marks) 6 (b) Explain activities tracking, defect tracking and issues tracking with respect to project tracking.(8 marks)
Answer any one question from Q7 and Q8
7 (a) What are the various functional modules of an ERP system? Explain.(8 marks) 7 (b) Explain any two implementation strategies for ERP in an organisation.(8 marks) 8 (a) Explain ERP implementation Life Cycle.(8 marks) 8 (b) List down 4 advantages and 4 myths of an ERP system.(8 marks)
Answer any one question from Q9 and Q10
9 (a) Write short note on:
i) Trends in SCM
ii) Software maintenance
iii) Reverse engineering(12 marks)
9 (b) What is software project auditing process and why it is essential?(6 marks)