1 (a) Draw an A-O-L diagram for the follwing data
Find-
i) Project duration
ii) Critical path
ii) Activity times
iv) Total ficam & free flaot values

<colgroup span="10"> </colgroup>
Activity A B C D E F G H I
Processor     A A - - B,D C,D G,H
Duration       5 2 3 5 4 3
12 marks

1 (b) Explain work Breakdown structure with an example. 12 marks

2 (a) A PERT Network details are given below
1) Calculate project operation corresponding to 70% probability
ii) Workout the probability of finishing the project in 22 days.

<colgroup span="10" width="85"> </colgroup>
Activity                  
T0 (days) 3 4 5 10 5 8 9 2 3
Tm (days) 6 6 7 12 6 10 10 4 6
Tg (days) 0       7 12 11 8 12

<colgroup span="7" width="85"> </colgroup>
      0 1 2 3
Probability (%)     50 84.13 97.72 99.87
12 marks

2 (b) (i) What is quality control? Explain the role of inspection in quality control. 12 marks

2 (b) (ii) Explain Economic order quantity. 12 marks

Explain

3 (a) (i) Quality Control 12 marks

3 (a) (ii) Network Rules. 12 marks

3 (b) Following data pertains to a construction project.

<colgroup span="8" width="85"> </colgroup>
Activity A B C D E F G
Predecessor   A - A C D,E B,C
Duration (days) 4 2 2 2 8 6 4
Resource / day 3 4 2 5 2 1 2

Work out the resources requirement on day to day basis when all activities are scheduled to start at their i) Early cates ii) late dates. Which of both schedules would you prefer? 12 marks

Explain

4 (a) (i) Functions of Material Management. 12 marks

4 (a) (ii) Define accident. Which are the costs associated with an accident? Explain. 12 marks

4 (b) (i) What are occupation health hazards? 12 marks

4 (b) (ii) Explain ABC analysis. 12 marks

5 (a) The details activity of given below.

<colgroup span="6" style="text-align: center;" width="85"> </colgroup>
Activity Predecessor Duration Cosr (Rs.)
Normal Crash Normal Crash
A - 4 2 5000 8000
B A 3 2 4000 6000
C -   2 7000 12000
D       7000 8000
E D   3 5000 8000
F B 4 2 10000 16000
G B,D 2 2 7000 10000
H A,C 7 1 3000 5000

Assuming a 12 marks

Distinguish Between:

5 (b) (i) CPM and PERT 12 marks

5 (b) (ii) A-O-A and A-O-N Network 12 marks

6 (a) What is a layout? 12 marks

6 (b) What is bar ? What an the short coming of bar chart? Also explain about 12 marks

Write notes on following

7 (a) Statistical Quantity 12 marks

7 (b) Occupational Health Hazards. 12 marks

7 (c) Time over Run & cos over Run 12 marks

7 (d) Minimum Wages Act 12 marks

7 (e) Updating of network 12 marks

7 (f) Sources of fuma 12 marks

7 (g) Costs of accidents. 12 marks