An operation involves the following elements given below with their related data.
Element Observed time(minutes) Rating Remarks
A 0.20 90 -
B 0.05 80 -
C 0.03 100 -
D 0.78 100 -
E 0.06 100 -
F 0.05 100 -
G 0.02 85 Once in 5 pieces
H 0.06 80 -
I 0.10 90 -
J 0.04 90 Once in 20 pieces

Assuming rest and personal allowances as 13% and contingency allowances as 2% calculate standard time of the job.

1 Answer
3
246views

Normal time = Observed time x Rating

Standard time = Normal Time x [ Contingency Allowances + Rest and Personal Allowances ]

Element Observed time (in mins) Rating Frequency Normal Time [(Observed time x Rating)/ (Frequency x 100)]
A 0.20 90 1 0.18
B 0.05 80 1 0.04
C 0.03 …