Construction Management Question Paper - Dec 16 - Civil Engineering (Semester 8) - Mumbai University (MU)
1 Answer
0
275views

Construction Management - Dec 16

Civil Engineering (Semester 8)

Total marks: 80
Total time: 3 Hours
INSTRUCTIONS
(1) Question 1 is compulsory.
(2) Attempt any three from the remaining questions.
(3) Draw neat diagrams wherever necessary.

1.a. Explain Principles of management given by Mr. Henry Fayol.
(10 marks) 11617

1.b. Explain the functions covered by Construction Management.
(10 marks) 8058

2.a. Details of activities of a construction project are given below. Draw network. Identify critical path. Determine values of total float, free float & independent float of all the activities.

Activity A B C D E F G H I J K L M N
Preceding Activity -- A A B D D D B C, E G F, I, J K G, H M
Duration (days) 5 2 6 12 10 9 5 9 1 2 3 9 7 9

(10 marks) 12286

2.b. What is Gantt bar chart? Also explain its drawbacks.
(10 marks) 11074

3.a. Following is the data of the associated with PERT Project.

Activity A B C D E F G
Preceding activity -- -- A B A B C & D
to (days) 6 5 4 4 4 2 4
tm (days) 9 8 7 7 7 5 10
tp (days) 12 17 22 16 10 8 22
Z -3 -2 -1 0 1 2 3
P (%) 0.13 2.28 15.87 50 84.13 97.72 99.87

i) Determine the variance of the project.

ii) What is the probability of completing the project in 29 days?

iii) What is the scheduled duration with 90% probability?

(10 marks) 12287

3.b. Define time and cost overrun. What are the common causes of time and cost overruns? Explain the corrective measures for the same.
(10 marks) 12281

4.a. Following Table shows activities, their durations and labour requirements:

Activity A (10-20) B (10-30) C (20-50) D (30-40) E (30-50) F (40-50)
Duration 8 11 6 5 8 5
Labours 3 4 2 5 3 3

i) Prepare histograms based on EST & LST Schedule.

ii) Which schedule you will prefer & why?

(10 marks) 12289

4.b. Explain: - i) Resource Levelling ii) Resource Smoothening.
(10 marks) 8098

5.a Determine the optimum cost and optimum duration for the project. The data for each activity of the network is given in the following table.

Indirect cost = Rs.160 / per day.

Activity Normal Time (days) Crash Time (days) Normal Cost (Rs.) Crash Cost (Rs.)
10-20 2 2 1000 1000
10-30 7 3 500 900
20-30 6 3 300 420
20-40 5 4 200 250
30-40 0 0 0 0
30-50 9 4 600 900
40-60 11 6 600 1000
50-60 6 3 700 910

(10 marks) 12305

5.b. Define Accident. Which are the main causes of accidents on construction sites? Also explain the precautionary measures to avoid accidents.
(10 marks) 8120

6. Write notes on followings: (Any five)

6.a. Role of inspection in quality control.
(4 marks) 11063

6.b. Principles of accounting.
(4 marks) 12291

6.c. Economic appraisal criteria's.
(4 marks) 12292

6.d. Work Breakdown Structure.
(4 marks) 8084

6.e. Time Value of Money.
(4 marks) 8100

6.f. A-B-C analysis.
(4 marks) 8101

6.g. Man-power planning.
(4 marks) 12293