Table below shows activities, their durations and labour requirements:
Activity Duration Labours
A (10-20) 4 3
B (10-30) 5 4
C (20-50) 7 2
D (30-40) 5 5
E (30-50) 4 3
F (40-50) 6 3

Draw Time scaled version network. Workout daily requirement of labours for all activities. Prepare histograms of EST & LST schedule. Which schedule you will prefer & why?