Work out the quantities of the following items of work by referring plan and section shown in figure.

a) P.C.C (1:2:4) in foundation

b) $1^{st}$ class brickwork in foundation in CM (1:4)

c) 2.5cm thick D.P.C (1:3:6)

d) 12 mm thick internal planter in CM (1:5)

1 Answer
0
7views

Step 1:

enter image description here

Total $C_L$ = 2 x 4.3 + 3 x 6 + 4 x 3.3 + 2 x 4.3 + 1.8 + 3.3

= 53.5m

No. of T junction = 10

Step 2:

enter image description here

Prepare abstract of cost for the items in above question

enter image description here