0
1.6kviews
Assume other required data.

Prepare an approximate estimate of cost for (G+1) RCC framed row house, constructed on plot of size 30 feet * 50 feet with FSI =1 Consider cost of construction of super structure = 800/sqft. Assume other required data.

Mumbai University > Civil Engineering > Sem 7 > Quantity Survey, Estimation and Valuation

Marks: 8 Marks

Year: Dec 2015

1 Answer
0
2views

1feet = 0.305m

Carpet area = 140m²

Carpet area /floor = 140*2 = 280m²

Total carpet area = 280 * 2 = 560 m²

Total built up area = C.A. + wall area + circulation area = 560 + 10/100*560 + 15/100 * 560

Total built up area = 700 m²

Cost of superstructure = 800/ m² = 700*800 = 560000

Cost of foundation = 20/100 * 560000 = 112000

Building cost = Foundation + superstructure = 672000

Cost of WC = 5/100 * 67200 = 33600

Cost of sanitation = 5/100 * 672000 = 33600

Cost of electrification = 7/100 * 672000 = 47040

Overall cost = 786240

Contingency = 5/100 * 786240 = 39327

Work charged establishment = 2.5/100 * 786240 = 19656

Final cost = OC + Contingency + WC = 1199223

How carpet area per floor is not been divided but multiplied ??? And cost is 800/sq ft you should convert it in metres to get answer in metres and FSI = Builtup area/plot of land , do we need to calculate carpet area first??


Please log in to add an answer.