Software Project Management : Question Paper May 2014 - Information Technology (Semester 7) | Mumbai University (MU)
1 Answer
0
1views

Software Project Management - May 2014

Information Technology (Semester 7)

TOTAL MARKS: 80
TOTAL TIME: 3 HOURS
(1) Question 1 is compulsory.
(2) Attempt any three from the remaining questions.
(3) Assume data if required.
(4) Figures to the right indicate full marks.
1(A) Solve are PMBOK knowledge areas?(5 marks) 1(B) Compare various project implementation approaches.(5 marks) 1(C) What is the need of IT project management?(5 marks) 1(D) Compare various formal organizational structure.(5 marks) 1(E) Define:
Scope grope,
Scope creep
Scope leap
Projectities
Earned values.
(5 marks)
2(A) Define project.Explain the attributes of project.(10 marks) 2(B) Explain project estimation techniques.(10 marks) 3(A) Explain the phases of project life cycle.Compare it with SDLC.(10 marks) 3(B) What is outsourcing?Explain project procurement management.(10 marks) 4(A) Explain IT project risk identification framework.(10 marks) 4(B) Explain the change management plan.(10 marks) 5(A) Explain the practices of exemplary leadership.What are the leadership styles?(10 marks) 5(B) Explain scope management processes.(10 marks) 6(A) Explain project planning framework(10 marks) 6(B)

Define critical path.Draw AON diagram, find critical path and float non critical path for following:

Activity Predecessor Duration in days
A --------- 6
B A 5
C A 8
D B,C 4
E C 3
F D 2
G D 4
H E,F,G 7
(10 marks)


Any Two

7(A) Write short on any
Ethical leadership and ethical dilemmas
(10 marks)
7(B) Resource loading(10 marks) 7(C) Project communication management(10 marks) 7(D) Work break down structure(10 marks)