0
3.2kviews
Software Project Management Question Paper - May 18 - Information Technology (Semester 7) - Mumbai University (MU)
1 Answer
0
67views

Software Project Management - May 18

Information Technology (Semester 7)

Total marks: 80
Total time: 3 Hours
INSTRUCTIONS
(1) Question No. 1 is compulsory.
(2) Attempt any three questions out of remaining five.
(3) Draw neat diagrams wherever necessary

Q1) Solve any four

1(a) What is milestone? Why are they useful?
(5 marks) 00

1(b) Explain business case.
(5 marks) 700

1(c) Give the difference between product oriented deliverable and project oriented deliverable.
(5 marks) 1831

1(d) Give the difference between PERT and CPM.
(5 marks) 716

1(e) What is projectitis? How can an organization minimize the likelihood of its occurrence?
(5 marks) 00

2(a) Explain the five phases of IT project methodology.
(10 marks) 699

2(b) Explain the five scope management processes?
(10 marks) 1832

3(a) Explain project estimation techniques.
(10 marks) 719

3(b) Explain in brief the objectives of procurement management.
(10 marks) 1839

4(a) Distinguish resource loading from resource leveling. Why is leveling of resource is preferred to large fluctuation.
(10 marks) 00

4(b) What is cost benefit analysis in projects? List the steps for performing costs benefit analysis.
(10 marks) 721

5(a) What is leadership? Explain various leadership styles.
(10 marks) 726 1836

5(b) What is project risk management? What are the RM processes?
(10 marks) 734

6(a) Discuss the statement: "Failing to define what not the part of the project is just as important as failing to define what is part of the project."
(10 marks) 00

6(b) What is meant by Communication Management? What is a channel in communication management? Explain the different channels generally used in a IT organization.
(10 marks) 00

Please log in to add an answer.