0
5.9kviews
Compare Gantt chart, Networking Diagram and PDM.
1 Answer
0
129views
Gantt Chart Networking Diagram PDM
Activities are represented as horizontal bars across the time axis. Graphically represents all of the project activities and tasks on nodes. Is a type of networking diagram and hence represents project activities and tasks on nodes.
Uses WBS as a reference. Uses WBS as a reference. Uses WBS as a reference.
No explicit information about logical sequence and dependencies between activities. Provides information about logical sequence and dependencies between activities. Provides information about logical sequence and dependencies between activities.
Does not use AON project diagramming technique. Uses AON project diagramming technique. Uses AON project diagramming technique.
Cannot specify lead and lag times. Cannot specify lead and lag times. Lead and lag times for activities can be specified.
Crashing of activities is not possible. Crashing of activities is possible. Crashing of activities is possible.
Please log in to add an answer.