Calculate the total elapsed time to complete both jobs.

Use graphical method to minimize the time required to process the following jobs on the machines. For each machine specify the job which should be done first. Also calculate the total elapsed time to complete both jobs. - enter image description here

1 Answer
0
71views

In the graph, the regions where the same machine intersects on the 2 jobs, is shaded, in order to show that the jobs cannot be processed on parallel at that part.

enter image description here

Total elapsed time = 22 hours

Machine A B C D E
Job 1 1st 2nd 2nd 2nd 2nd
Job 2 2nd 1st 1st 1st 1st