Draw the Network
| written 9.4 years ago by | modified 3.9 years ago by |
The interdependence of a job consisting of 7 activities & time estimates are given in following table.
Draw Network & Determine:-
1) Project duration corresponding to 50 % probability..
2) Probability of completing the project in 35 days.
| Z | -3 | -2 | -1 | 0 | 1 | 2 | 3 |
|---|---|---|---|---|---|---|---|
| P(%) | 0.13 | 2.28 | 15.87 | 50 | 84.13 | 97.72 | 99.87 |
| Activity | Preceding Activity | Succeeding Activity | $T_0$ | $T_m$ | $T_p$ |
|---|---|---|---|---|---|
| A | - | C & E | 6 | 9 | 12 |
| B | - | D & E | 5 | 8 | 17 |
| C | A | G | 4 | 7 | 22 |
| D | B | G | 4 | 7 | 16 |
| E | A | - | 4 | 7 | 10 |
| F | B | - | 2 | 5 | 8 |
| G | C & D | - | 4 | 10 | 22 |