Prepare a resource histogram based on EST And LST.
| written 9.4 years ago by | • modified 3.9 years ago |
Table as shown below:
| Activity | A(1-2) | B(2-3) | C(2-4) | D(3-5) | E(4-5) | F(5-6) |
|---|---|---|---|---|---|---|
| Duration(Days) | 3 | 4 | 5 | 6 | 4 | 3 |
| Masons | 4 | 3 | 2 | 4 | 3 | 2 |