Prepare time scaled version network and histogram for EST and LST schedule.
| written 9.3 years ago by | modified 3.8 years ago by |
Following table shows activities, their durations and labour requirement.
| Activity | Immediate Predecessor | Duration (days) | Labours |
|---|---|---|---|
| A | - | 4 | 9 |
| B | - | 2 | 3 |
| C | - | 2 | 6 |
| D | - | 4 | 4 |
| E | B | 3\ 8\ | |
| F | C | 2 | 7 |
| G | D, F | 3 | 2 |
| H | E, G | 4 | 1 |
Prepare time scaled version network and histogram for EST and LST schedule. Which schedule will you prefer? Why?