0
1.6kviews
Prepare resource histogram based on EST and LFT schedule and comment the suitability of distribution

For a small project, prepare resource histogram based on EST and LFT schedule and comment the suitability of distribution on above methods.

Activity Preceding Activity Duration (day) Workers
A - 4 2
B - 5 3
C - 3 5
D A 4 4
E B 5 3
F C 3 5
G E 7 6


1 Answer
0
10views
Activity Preceding Activity Duration (day) EST EFT LST LFT Workers
A - 4 0 4 9 13 2
B - 5 0 5 0 5 3
C - 3 0 3 11 14 5
D A 4 4 8 13 17 4
E B 5 5 10 5 10 3 …

Create a free account to keep reading this post.

and 2 others joined a min ago.

Please log in to add an answer.