Work out the quantities of following items.

Work out the quantities of following items from given plan& section

  1. 12mm thick internal plastering in CM 1:4
  2. Brickwork (CM 1:6) in superstructure of ground floor
  3. Concrete in footing
  4. Flooring & Skirting
1 Answer
0
4views

enter image description here

enter image description here

$\text{Trapezoidal portion} \\ V= \bigg(\dfrac{A1+A2}{2}\bigg) *H \\ = \bigg(\dfrac{0.38*0.38+1.2*1.27*0.4}{2}\bigg) \\ = 0.333 m²$ $\hspace{5cm}$ $\text{Trapezoidal portion} \\ V= \bigg(\dfrac{A1+A2}{2}\bigg) *H \\ = \bigg(\dfrac{0.38*0.48+1.2*1.37*0.5}{2}\bigg) \\ = 0.456 m²$

$\text{Rectangular portion} \\ = 1.2*1.27*0.15 \\ = 0.22 m³ \\ VF1 = 0.333+0.22 \\ = 0.553 m³$ $\hspace{7.5cm}$ $\text{Rectangular portion} \\ = 1.2*1.37*0.15 …