| written 9.8 years ago by |
Software Project Management - May 2015
Information Technology (Semester 8)
TOTAL MARKS: 100
TOTAL TIME: 3 HOURS
(1) Question 1 is compulsory.
(2) Attempt any four from the remaining questions.
(3) Assume data wherever required.
(4) Figures to the right indicate full marks.
1 (a) What is outsourcing? What are its advantages and disadvantages?(5 marks)
1 (b) What is project management? Why is it needed?(5 marks)
1 (c) Define project. What are the attributes of project?(5 marks)
1 (d) What is project integration management?(5 marks)
1 (e) What is relation between MOV, scope and WBS(5 marks)
2 (a) Explain project procurement management.(10 marks)
2 (b) What are the methods of budgeting for a project?(10 marks)
3 (a) Explain the project Scheduling techniques.(10 marks)
3 (b) Explain IT project risk identification framework.(10 marks)
4 (a) Explain the various leadership styles.(10 marks)
4 (b) Explain the project change management plan.(10 marks)
5 (a) Explain scope management plan.(10 marks)
5 (b) Explain the project implementation approaches.(10 marks)
6 (a) Explain project planning framework.(10 marks)
6 (b) Define critical path. Draw AON diagram and find critical path for
| Activity | Predecessor | Duration in days |
| A | - | 2 |
| B | A | 5 |
| C | A | 2 |
| D | B | 5 |
| E | B | 5 |
| F | C | 5 |
| G | D | 1 |
| H | D | 1 |
| I | G | 2 |
| J | E, F, H, I | 1 |
Write short note on any two:
7 (a) Resource loading and resource levelling.(10 marks) 7 (b) Dealing with resistance and conflicts in project.(10 marks) 7 (c) Project communication plan(10 marks)