The Three time estimate for different activities of a project are given below

Mumbai University > Civil Engineering > SEM 8 > Construction Management

Marks: 10M

The Three time estimate for different activities of a project are given below:-

Activity T0 Tm Tp
1-2 2 5 8
2-3 4 9 20
2-4 4 7 16
2-5 8 11 20
3-6 3 7 17
4-6 7 10 13
4-5 0 0 0
5-7 3 5 13
6-7 2 3 10
7-8 2 4 6
Z -2 -1 0 1 2
P% -2.28 15.87 50 84.13 97.72

What is the probability of completing the project in 35 Days?

1 Answer
0
135views

Step 1 :-

For critical activity only

$\sigma = \frac{t_p-t_0}{6}$

Activity T0 Tm Tp $t_e = \frac{t_0+4t_m+t_p}{6}$ $\sigma$ $\sigma$
1-2 2 5 8 5 1 1
2-3 4 9 20 6
2-4 4 7 16 8 2 4
2-5 8 11 20 12
3-6 3 7 17 8
4-6 7 …