0
1.5kviews
The interdependence of a job consisting of 7 activities & time estimates are given in following table.

Mumbai University > Civil Engineering > SEM 8 > Construction Management

Marks: 12M

Draw Network & Determine:-

1) Project duration corresponding to 50 % probability.

2) Probability of completing the project in 35 days.

Z -3 -2 -1 0 1 2 3
P(%) 0.13 2.28 15.87 50 84.13 97.72 99.87
1 Answer
0
27views
Activity Preceding Activity Succeeding Activity $T_0$ $T_m$ $T_p$
A - C &E 6 9 12
B - D & E 5 8 17
C A G 4 7 22
D B G 4 7 16
E A - 4 7 10
F B - 2 5 8
G C & …