The interdependence of a job consisting of 7 activities & time estimates are given in following table.
| written 8.0 years ago by | • modified 3.9 years ago |
Mumbai University > Civil Engineering > SEM 8 > Construction Management
Marks: 12M
Draw Network & Determine:-
1) Project duration corresponding to 50 % probability.
2) Probability of completing the project in 35 days.
| Z | -3 | -2 | -1 | 0 | 1 | 2 | 3 |
|---|---|---|---|---|---|---|---|
| P(%) | 0.13 | 2.28 | 15.87 | 50 | 84.13 | 97.72 | 99.87 |