Draw network and identify critical path
written 6.4 years ago by | modified 2.1 years ago by |
Details of activities of a construction project are given below. Draw network. Identify critical path. Determine values of total float, free float & independent float of all the activities.
Activity | Preceding Activity | Duration (days) |
---|---|---|
A | - | 5 |
B | A | 2 |
C | A | 6 |
D | B | 12 |
E | D | 10 |
F | D | 9 |
G | D | 5 |
H | B | 9 |
I | C, E | 1 |
J | G | 2 |
K | F, I, J | 3 |
L | K | 9 |
M | G, H | 7 |
N | M | 9 |