Draw network and identify critical path

Details of activities of a construction project are given below. Draw network. Identify critical path. Determine values of total float, free float & independent float of all the activities.

Activity Preceding Activity Duration (days)
A - 5
B A 2
C A 6
D B 12
E D 10
F D 9
G D 5
H B 9
I C, E 1
J G 2
K F, I, J 3
L K 9
M G, H 7
N M 9