Draw network. Identify critical path

Mumbai University > Civil Engineering > SEM 8 > Construction Management

Marks: 12M

Details of activities of a construction project are given below. Draw network. Identify critical path. Determine values of total float, free float & independent float of all the activities.

Activity Preceding Activity Duration (days)
A - 5
B A 2
C A 6
D B 12
E D 10
F D 9
G D 5
H B 9
I C, E 1
J G 2
K F, I, J 3
L K 9
M G, H 7
N M 9
1 Answer
1
8views
Activity Preceding Activity Duration (days) EST EFT LST LFT TF FF Ind F
A - 5 0 5 0 5 0 0 0
B A 2 5 7 5 7 0 0 0
C A 6 5 11 23 29 18 18 18
D B 12 7 19 7 19 …