Draw network. Identify critical path
| written 8.0 years ago by | • modified 3.9 years ago |
Mumbai University > Civil Engineering > SEM 8 > Construction Management
Marks: 12M
Details of activities of a construction project are given below. Draw network. Identify critical path. Determine values of total float, free float & independent float of all the activities.
| Activity | Preceding Activity | Duration (days) |
|---|---|---|
| A | - | 5 |
| B | A | 2 |
| C | A | 6 |
| D | B | 12 |
| E | D | 10 |
| F | D | 9 |
| G | D | 5 |
| H | B | 9 |
| I | C, E | 1 |
| J | G | 2 |
| K | F, I, J | 3 |
| L | K | 9 |
| M | G, H | 7 |
| N | M | 9 |