Draw an A-O-L diagram
| written 8.0 years ago by | • modified 3.9 years ago |
Mumbai University > Civil Engineering > SEM 8 > Construction Management
Marks: 10M
Draw an A-O-L diagram for the following data:-
Find:-
1) Project duration
2) Critical Path
3) Activity times
4) Total float & free float values.
| Activity | Predecessor | Duration (days) |
|---|---|---|
| A | - | 4 |
| B | A | 5 |
| C | A | 3 |
| D | A | 5 |
| E | - | 2 |
| F | - | 3 |
| G | B, D | 5 |
| H | C, D | 4 |
| I | G, H | 3 |