Identify the project duration & critical path.

Mumbai University > Civil Engineering > SEM 8 > Construction Management

Marks: 12M

A network consists of the following activities:

a) Draw the networks.

b) workout the floats.

c) Identify the project duration & critical path.

Sr. No. Activity Preceding Activity Following Activity Duration (days)
1 P - U 15
2 Q - S, T 19
3 R - - 29
4 S Q V, W 14
5 T Q X 09
6 U P X 14
7 V S X 02
8 W S - 15
9 X U, V, T - 11
1 Answer
0
11views
Activity Preceding Activity Duration (days) EST EFT LST LFT TF FF Int F Ind F
P - 15 0 15 8 23 8 0 8 0
Q - 19 0 19 0 19 0 0 0 0
R - 29 0 29 19 48 19 19 0 19
S Q 14 19 33 19 33 0 0 0 0
T Q 09 19 28 28 37 9 7 2 7
U P 14 15 29 23 37 8 6 2 -2
V S 02 33 35 35 37 2 0 2 0
W S 15 33 48 33 48 0 0 0 0
X U, V, T 11 35 46 37 48 2 2 0 0

Project duration = 48 days

enter image description here

Critical path = 10-30-40-60

Critical activity = Q-S-W