Draw network. Identify the critical path. Determine values of total float, free float and independent float of all activities.

Detail of activities of construction project are given below. Draw network. Identify the critical path. Determine values of total float, free float and independent float of all activities.

Activity A B C D E F G H I J K L M N
Preceding Activity -- A A B D D D B C,F G F,I,J K G,H M
Duration 5 2 6 12 10 9 5 9 1 2 3 9 7 9
1 Answer
0
73views
Activity Preceding Activity Duration EST EFT LST LFT TF FF IF
A -- 5 0 5 0 5 0 0 0
B A 2 5 7 5 7 0 0 0
C A 6 5 11 22 28 17 2 17
D B 12 7 19 7 19 0 0 …