Draw network. Identify the critical path. Determine values of total float, free float and independent float of all activities.
| written 8.0 years ago by | modified 3.1 years ago by |
Detail of activities of construction project are given below. Draw network. Identify the critical path. Determine values of total float, free float and independent float of all activities.
| Activity | A | B | C | D | E | F | G | H | I | J | K | L | M | N |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Preceding Activity | -- | A | A | B | D | D | D | B | C,F | G | F,I,J | K | G,H | M |
| Duration | 5 | 2 | 6 | 12 | 10 | 9 | 5 | 9 | 1 | 2 | 3 | 9 | 7 | 9 |