0
1.4kviews
Following data pertains to a construction project.

Following data pertains to a construction project.

Activity A B C D E F G
Predecessor - A - A C D, E B, C
Duration 4 2 2 2 8 6 4
Resource / Day 3 4 2 5 2 1 2

Workout the resources requirements on day to day basis. When all activities are scheduled to start at their:

1) Early dates,

2) Late dates.

Which of both schedules would you prefer?

1 Answer
0
4views
Activity Predecessor Duration EST EFT LST LFT Resource/ day
A - 4 0 4 4 8 3
B A 2 4 6 10 12 4
C - 2 0 2 0 2 2
D A 2 4 6 8 10 5
E C 8 2 10 2 10 2
F …

Create a free account to keep reading this post.

and 5 others joined a min ago.

Please log in to add an answer.