Following data pertains to a construction project.
| written 8.0 years ago by | modified 3.8 years ago by |
Following data pertains to a construction project.
| Activity | A B | C | D | E | F | G | |
|---|---|---|---|---|---|---|---|
| Predecessor | - | A | - | A | C | D, E | B, C |
| Duration | 4 | 2 | 2 | 2 | 8 | 6 | 4 |
| Resource / Day | 3 | 4 | 2 | 5 | 2 | 1 | 2 |
Workout the resources requirements on day to day basis. When all activities are scheduled to start at their:
1) Early dates,
2) Late dates.
Which of both schedules would you prefer?