Following data pertains to a construction project.
written 6.9 years ago by | modified 2.7 years ago by |
Following data pertains to a construction project.
Activity | A B | C | D | E | F | G | |
---|---|---|---|---|---|---|---|
Predecessor | - | A | - | A | C | D, E | B, C |
Duration | 4 | 2 | 2 | 2 | 8 | 6 | 4 |
Resource / Day | 3 | 4 | 2 | 5 | 2 | 1 | 2 |
Workout the resources requirements on day to day basis. When all activities are scheduled to start at their:
1) Early dates,
2) Late dates.
Which of both schedules would you prefer?