For a small project, prepare resource histogram based on EST and LFT schedule and comment the suitability of distribution on above methods.
| Activity | Preceding Activity | Duration (day) | Workers |
|---|---|---|---|
| A | - | 4 | 2 |
| B | - | 5 | 3 |
| C | - | 3 | 5 |
| D | A | 4 | 4 |
| E | B | 5 | 3 |
| F | C | 3 | 5 |
| G | E | 7 | 6 |