320fatigue and delay allowances are set at 15%. The molding machine operator is rated at 110% and the packer is rated at 80%. Observed times per batch are given below.
| written 7.9 years ago by | modified 3.7 years ago by |
| Observed Time in Minutes | ||||
|---|---|---|---|---|
| Task | 1 | 2 | 3 | 4 |
| Moulding | 26 | 30 | 29 | 31 |
| Packing | 45 | 50 | 35 | 30 |
Determine the Normal and standard times for both tasks.