MU Civil Engineering (Semester 8)
Total marks: 80
Total time: 3 Hours
INSTRUCTIONS
(1) Assume appropriate data and state your reasons
(2) Marks are given to the right of every question
(3) Draw neat diagrams wherever necessary
1(a) Following is the data associated with small construction Project. Draw Network. Calculate event Times. Identify Critical Path, Also determine Values of all types of floats.
Activity |
A |
B |
C |
D |
E |
F |
G |
Preceeding Activity |
----- |
A |
A |
A |
B |
D |
C,E,F |
Duration(days). |
5 |
4 |
7 |
5 |
3 |
4 |
7 |
10 marks
12303
1(b) Explain, Henry Fayol's 14 Principles of Management.
10 marks
11617
2(a) Following is the data associated with a small Project.
Activity |
1-2 |
1-3 |
1-4 |
2-5 |
3-5 |
4-6 |
5-6 |
To(weekss) |
1 |
1 |
2 |
1 |
2 |
2 |
3 |
Tm(weeks) |
1 |
4 |
2 |
1 |
5 |
5 |
6 |
Tp(weeks) |
7 |
7 |
8 |
1 |
14 |
8 |
15 |
Z |
-3 |
-2 |
-1 |
0 |
1 |
2 |
3 |
P(%) |
0.13 |
2.28 |
15.87 |
50 |
84.13 |
97.72 |
99.87 |
Determine standard Deviation & Variance of the Project. Also determine the Probability of completing the project at :-
i) Expected duration ii) 3 weeks earlier than expected duraiton
iii) 3 weeks later than expected duration.
10 marks
12304
2(b) What is Quality control? Explain the role of inspection in quality control
10 marks
11063
3(a) Determine optimum cost of optimum duration for the following data of a project . Indirect Cost of project = Rs. 1000/day.
Activity |
1-2 |
1-3 |
2-3 |
2-4 |
3-4 |
4-5 |
National Duration(days) |
6 |
8 |
4 |
5 |
5 |
7 |
Crash Duration (days) |
3 |
5 |
1 |
3 |
3 |
4 |
Normal Cost (Rs). |
7000 |
4000 |
6000 |
8000 |
5000 |
8000 |
Crash Cost ( Rs) |
14500 |
8500 |
9000 |
15000 |
11000 |
15000 |
10 marks
12305
3(b) What do you understand by "Updating of Project? What information is required while updating? Explain the stepwise procedure of updating.
10 marks
11070
4(a) Table below shows activites, their durations and labour requirements:
Activity |
Duration |
Carpenters |
A (1-2) |
8 |
3 |
B (1-3) |
11 |
4 |
C (2-5) |
6 |
2 |
D (3-4) |
5 |
5 |
E(3-5) |
8 |
3 |
F (4-5) |
5 |
3 |
Workout daily requirement of carpenters with all activity schedule to start at their EST, LST. Also prepare historgam. Comment which schedule will you prefer &why?
10 marks
12289
4(b) Explain Resurce Smoothening & Resource Levelling.
10 marks
8098
5(a) Explain the functions of Human Resource Management.
10 marks
11081
5(b) What is accounting? Explain generally accepted principles of an accounting.
10 marks
12291
Write short note any five question from Q.6(a, b, c, d, e,f )
6(a) Job Layout
10 marks
11075
6(b) Work Breakdown Structure
10 marks
8084
6(c) Net Present value
10 marks
12307
6(d) ISO 14000
10 marks
11064
6(e) Time Over-run & Cost Over-run
10 marks
12281
6(f) Contribution of Mr.Taylor.
10 marks
12308