The work study engineer carries out the work sampling study. The following observations were made for the machine shop. Compute the standard time for the job
The duration of study 120
Total number of observations 7000
No. of working activities 1200
Ratio of manual to machine element 2:1
Average rating factor 120%
Total no. of jobs produced during study 800
Rest and personal allowances 17%