0
700views
The activity details of a small network is shown in the table below
Activity 1-2 1-3 1-4 2-5 3-6 4-5 4-6 4-7 5-7 6-7
Time required 6 7 4 Dummy activity 4 12 10 8 5 6

The following conditions exist at the end of 10 days:
i) Activity 1-2, 1-3 and 1-4 have been completed as originally scheduled.
ii) Activity 4-5 is in progress and will require 6 more days for its completion.
iii) Activity 4-6 is in progress and still require 6 more days for its completion.
iv) Activity 3-6 is in progress and will be completed in one day.
v) Other activities have not been commenced and their original predicted duration will hold good, except for activity 5-7 which will require only three days instead of 5 days originally planned.
Update the network and determine the critical path of the updated network. What is the total increase in the project duration?

Please log in to add an answer.