The activity details of a small network is shown in the table below
written 5.1 years ago by | • modified 4.0 years ago |
Activity | 1-2 | 1-3 | 1-4 | 2-5 | 3-6 | 4-5 | 4-6 | 4-7 | 5-7 | 6-7 |
---|---|---|---|---|---|---|---|---|---|---|
Time required | 6 | 7 | 4 | Dummy activity | 4 | 12 | 10 | 8 | 5 | 6 |
The following conditions exist at the end of 10 days:
i) Activity 1-2, 1-3 and 1-4 have been completed as originally scheduled.
ii) Activity 4-5 is in progress and will require 6 more days for its completion.
iii) Activity 4-6 is in progress and still require 6 more days for its completion.
iv) Activity 3-6 is in progress and will be completed in one day.
v) Other activities have not been commenced and their original predicted duration will hold good, except for activity 5-7 which will require only three days instead of 5 days originally planned.
Update the network and determine the critical path of the updated network. What is the total increase in the project duration?