Details of activities of a construction project are given below.
| written 6.7 years ago by | modified 3.6 years ago by |
Identify critical path. Determine values of total float, free float & independent float of all the activities.
| Activity | A | B | C | D | E | F | G | H | I | J | K | L | M | N |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Preceding Activity | -- | A | A | B | D | D | D | B | C, E | G | F, I, J | K | G, H | M |
| Duration (days) | 5 | 2 | 6 | 12 | 10 | 9 | 5 | 9 | 1 | 2 | 3 | 9 | 7 | 9 |