Determine the optimum cost and optimum duration for the project. The data for each activity of the network is given in the following table.

Indirect cost = Rs.160 / per day.

Activity Normal Time (days) Crash Time (days) Normal Cost (Rs.) Crash Cost (Rs.)
10-20 2 2 1000 1000
10-30 7 3 500 900
20-30 6 3 300 420
20-40 5 4 200 250
30-40 0 0 0 0
30-50 9 4 600 900
40-60 11 6 600 1000
50-60 6 3 700 910