Following is the data associated with small construction Project.
| written 6.8 years ago by | • modified 5.7 years ago |
Draw Network. Calculate event Times. Identify Critical Path, Also determine Values of all types of floats.
| Activity | A | B | C | D | E | F | G |
| Preceeding Activity | ----- | A | A | A | B | D | C,E,F |
| Duration(days). | 5 | 4 | 7 | 5 | 3 | 4 | 7 |