The following table shows the details of activities of a small project. Calculate the optimum project cost & project duration. Indirect cost = Rs. 1500 / per day
| written 6.7 years ago by | • modified 5.6 years ago |
| Activity | Predecessor | Normal | Normal | Crash | Crash |
|---|---|---|---|---|---|
| Time (days) | Cost (Rs) | Time (days) | Cost (Rs) | ||
| A | ---- | 9 | 8000 | 6 | 9500 |
| B | ---- | 5 | 5000 | 3 | 5500 |
| C | B | 7 | 6500 | 4 | 10500 |
| D | A | 6 | 7000 | 4 | 10000 |
| E | A | 5 | 4500 | 3 | 7500 |
| F | D | 9 | 5500 | 5 | 9000 |