Table below shows activities, their durations and labour requirements:
| written 6.7 years ago by | • modified 5.6 years ago |
| Activity | Duration | Labours |
|---|---|---|
| A (10-20) | 4 | 3 |
| B (10-30) | 5 | 4 |
| C (20-50) | 7 | 2 |
| D (30-40) | 5 | 5 |
| E (30-50) | 4 | 3 |
| F (40-50) | 6 | 3 |
Draw Time scaled version network. Workout daily requirement of labours for all activities. Prepare histograms of EST & LST schedule. Which schedule you will prefer & why?