The following table shows the details of activities of a small work. Construct the network of the project.Determine optimum project cost & optimum duration. Indirect cost/day = Rs.700 /-
| written 6.7 years ago by | • modified 5.6 years ago |
| Activity | Predecessor | Normal | Normal | Crash | Crash |
|---|---|---|---|---|---|
| Time (days) | Cost (Rs) | Time (days) | Cost (Rs) | ||
| A | ---- | 9 | 8000 | 6 | 9500 |
| B | ---- | 5 | 5000 | 3 | 5500 |
| C | B | 5 | 5000 | 3 | 5500 |
| D | A | 7 | 4000 | 4 | 7500 |
| E | A | 5 | 5500 | 3 | 7000 |
| F | D | 6 | 8000 | 4 | 10000 |