Activity data for a small project is given in the following table
| written 6.7 years ago by | • modified 5.6 years ago |
| Activity | A | B | C | D | E | F | G | H | I |
|---|---|---|---|---|---|---|---|---|---|
| Preceding Activity | -- | -- | -- | A | B | C | D, E | B | H, F |
| Duration (days) | 3 | 5 | 4 | 2 | 3 | 9 | 8 | 7 | 9 |
i- Draw AOA Network
ii- Work out activity times and floats
iii- Determine project duration and critical