Draw AON diagram and find the activities on critical path. Calculate minimum Overall project completion time. What is float time associated with each of non-critical activities?
| written 9.5 years ago by | • modified 5.0 years ago |
| Activity | Duration(wrks) | Immediate Predecessor |
|---|---|---|
| A | 2 | - |
| B | 3 | - |
| C | 4 | A |
| D | 3 | A,B |
| E | 8 | C,D |
| F | 3 | C |
| G | 2 | E |
| H | 3 | F,G |