Electronics And Communication Engineering (Semester 5)
Total marks: 80
Total time: 3 Hours
Note: Answer FIVE full questions, choosing ONE full question form each module.
Module-1
1.a.
Classify management into three levels.
(3 marks)
00
1.b.
Summarize briefly 3 types of managerial skills.
(6 marks)
00
1.c.
Analyse management as science and also as an art.
(7 marks)
00
OR
2.a.
Define planning. Explain any six limitations of planning.
(7 marks)
00
2.b.
Illustrate and explain different blocks of decision making process.
(9 marks)
00
Module-2
3.a.
Select and describe important steps in the process of organising.
(5 marks)
00
3.b.
Explain the advantages and disadvantages of committees in an organization.
(5 marks)
00
3.c.
Summarize any six types of recruitment process.
(6 marks)
00
OR
4.a.
What is direction in an organization? Explain any five techniques of co-ordination.
(6 marks)
00
4.b.
Explain the three basic steps in a control process.
(6 marks)
00
4.c.
List four important characteristics of leadership.
(4 marks)
00
Module-3
5.a.
Why is social audit required?
(2 marks)
00
5.b.
Illustrate the social responsibilities of business towards different groups.
(8 marks)
00
5.c.
List out the advantages of corporate governance.
(6 marks)
00
OR
6.a.
Explain any four characteristics of successful entrepreneurship.
(8 marks)
00
6.b.
Summarize capacity building of entrepreneurship.
(8 marks)
00
Module-4
7.a.
Explain any four rules of small Scale industries (SSI) in economic development.
(8 marks)
00
7.b.
Define Ancillary industry and Tiny industry.
(4 marks)
00
7.c.
Outline any four reasons for sickness in SSI sector.
(4 marks)
00
OR
8.
Summarize any four state level or central level instructions that supports small business enterprises.
(16 marks)
00
Module-5
9.a.
List any four characteristics of project.
(4 marks)
00
9.b.
Classify projects into different type based on various parameters.
(5 marks)
00
9.c.
What is project formulation? Explain any major steps involved in project formulation.
(7 marks)
00
OR
10.a.
Mention various steps involved in PERT analysis.
(10 marks)
00
10.b.
List out the advantages and limitations of CPM.
(4 marks)
00
10.c.
Show the relation between project design and network using block diagram.
(2 marks)
00