Mechanical Engineering (Semester 5)
Total marks: 70
Total time: 3 Hours
INSTRUCTIONS
(1) Question 1 is compulsory.
(2) Attempt Q1 or Q2, Q3 or Q4, Q5 or Q6, Q7 or Q8, Q9 or Q10.
(3) Draw neat diagrams wherever necessary.
1.a.
Differentiate between Precision \& Accuracy with suitable examples.
(5 marks)
00
1.b.
Determine the tolerance on hole and shaft for a precision running fit
designated by 40 $\mathrm{H} 7 \mathrm{g} 6.40 \mathrm{mm}$ lies in the diameter step of $30-50 \mathrm{mm}$ .
$\mathrm{i}=0.45(\mathrm{D}) \mathrm{X}+0.001 \mathrm{D}$ -microns. Fundamental deviation of $\mathrm{g}$ shaft $=-2.5 \mathrm{D}^{0.34}$ State the actual maximum and minimum size of both hole
and shaft. $\mathrm{IT} 7=16 \mathrm{i}, \mathrm{ITT} 6=10 \mathrm{i}$ .
(5 marks)
00
OR
2.a.
Explain any one method of assessing the surface finish.
(5 marks)
00
2.b.
Explain tool makers microscope $\&$ their application.
(5 marks)
00
3.a.
Explain laser interferometer $\&$ its application.
(5 marks)
00
3.b.
Write short note on machine vision system.
(5 marks)
00
OR
4.a.
State $\&$ explain Taylor's principle of gauge design with example.
(5 marks)
00
4.b.
Explain method of measuring effective diameter using two wires with
neat sketch.
(5 marks)
00
5.a.
Explain Jurans triology approach with diagram.
(5 marks)
00
5.b.
State seven new quality tools. Explain any three in detail.
(8 marks)
00
OR
6.a.
What is cost of quality? Explain Cost of failure, cost of appraisal $\&$
Cost of prevention.
(8 marks)
00
6.b.
What is initial planning for quality? Explain in details.
(8 marks)
00
7.a.
What are advantages of sampling inspection over 100$\%$ inspection?
Explain the difference between Single sampling \& Double sampling plan.
(8 marks)
00
7.b.
Following is the record for successive lots of part being produced by
plastic molding press. As each lot is come off the line a random sample
of 150 pieces were inspected (results are expressed to the nearest
0.1$\%$ ). Calculate $\overline{p}$ , Control limits \& plot control chart and comment.
| Lot no. |
Sample size |
No. of defectives |
| 1 |
150 |
4 |
| 2 |
150 |
8 |
| 3 |
150 |
2 |
| 4 |
150 |
4 |
| 5 |
150 |
4 |
| 6 |
150 |
6 |
| 7 |
150 |
10 |
| 8 |
150 |
4 |
| 9 |
150 |
6 |
| 10 |
150 |
8 |
(8 marks)
00
OR
8.a.
Write short note on OC curve $\&$ its characteristics.
(8 marks)
00
8.b.
Explain single sampling plan with flow chart. For the given data calculate
sample size and AOQ for single sampling plan.
i) Probability of acceptance for 0.3$\%$ defectives in a lot is 0.558
ii) Lot size $\mathrm{N}=10000$ - anits
iii) $\mathrm{np}^{\prime}=1,5$
iv) Acceptance number $\mathrm{c}=1$
v) Defectives found in the sample are not to be replaced.
(8 marks)
00
Write short note on (Any three):
9.b.
Zero defects
(6 marks)
00
9.d.
TS-16949
(6 marks)
00
9.e.
Quality audit.
(6 marks)
00