Estimate the quantities of the following items
1 Answer
| written 6.3 years ago by |

1) Earthwork in an excavation in the foundation. 2) Lime concrete in foundation 3) First class brickwork in cement mortar (1:4) in foundation and plinth. 4) First class brickwork in cement mortar (1:6) in superstructure. Neglect step.
(A) By centre line method:
(a) Length of centre line for mainwalls = …