Work out the quantities from given plan and section.
| written 9.5 years ago by | • modified 5.9 years ago |
a) Excavation in ordinary soil.
b) UCR masonry in foundation in CM (1:4)
c) RCC quantities for slab, band lintel (150mm thk) and chajja in M25 grod of concrete
d) External plastering in CM 1:3, 15 mm thick
ADD COMMENT
EDIT
1 Answer

and 2 others joined a min ago.


and 4 others joined a min ago.
Please check the answer of 2nd footing. I think it is 36.4 cu. m.