Difference between Critical path method and Gantt chart
1 Answer
0
315views

Critical path method (CPM):

  • It visualizes critical and non-critical paths and calculates project duration.

  • It is dsplayed as network diagram with linked boxes.

  • CPM doesn’t show resources required

  • CPM plots activities on network diagram without timescale.

Gantt chart:

  • It visualizes how project activities are progressing.

  • Gantt chart is displayed as horizontal bar chart.

  • It shows resources required for each activity.

  • It plots activities on a timescale.